| Commercial Vehicle Permits And Restrictions. |
| Permit Status - Interstate 35 |
Interstate 35: at MN 23 road closed, bridge construction, width limit in effect -- detour in operation Width limit 12 ' 0 " — until August 20 Comment: Bridge removal and re-construction at I-35 and the south jct. of MN 23, south of Hinckley. Starting July 27th, all ON and OFF ramps for I-35 at will be closed for a period of ten working days. Traffic will be detoured onto Pine County 61, Pine County 48 and also on I-35. last updated July 21 |
| |
| Permit Status - Interstate 35 |
Interstate 35 in both directions: from Exit 209 Pine County Road 46 to Exit 227 Carlton County Road 4 roadway reduced to two lanes, width limit in effect, single line traffic - alternating directions Width limit 12 ' 0 " — until September 15 Comment: On I-35 from Mahtowa to Sturgeon Lake NB I-35 will be routed onto SB I-35 with single lane traffic in each direction. last updated July 26 |
| |
| Permit Status - Interstate 35 |
Interstate 35: from Exit 249 Boundary Avenue to Exit 258 21st Avenue East major road construction, width limit in effect, speed restrictions in force, roadway reduced to one lane -- trucks are recommended to avoid the area, drive with extreme caution Width limit 11 ' 0 ", Advisory speed limit 45 MPH — until October 30 Comment: In Duluth from Boundary Avenue to 21st Avenue East, all traffic will be switched onto the NB lanes of I-35. Motorists are urged to proceed with caution due to construction activities and ramp closures. For more information CLICK HERE last updated June 24 |
| |
| Permit Status - Interstate 35 |
Interstate 35: from Exit 258 21st Avenue East to MN 61 road closed to traffic, major road construction, width limit in effect, length limit in effect -- follow the detour signs — until October 30 Comment: In Duluth traffic will be detoured off NB I-35 at the 21st Avenue east exit ramp. Traffic will follow marked detour route to London Road. SB I-35 traffic will enter the freeway at 21st Avenue East. An addditional detour will be placed on London Road. Southbound traffic will be routed to Superior St. at 40th Avene east last updated yesterday at 10:12 AM CDT |
| |
| Permit Status - Interstate 90 |
Interstate 90: from Exit 175 Oakland Avenue West to Exit 181 28th Street Northeast roadway reduced to one lane, major road construction, width limit in effect, length limit in effect Vehicle length limit 75.0 ft, Width limit 11 ' 0 " — until October 15 Comment: Daytime lane closures and traffic bypasses. For more information on this project CLICK HERE last updated April 16 |
| |
| Permit Status - Interstate 90 |
Interstate 90 westbound: from after MN 56 to MN 16 road construction, roadway reduced to one lane, width limit in effect Width limit 10 ' 0 " — until September 15 Comment: Concrete Pavement Rehabilitation, Grinding and Biruminous Should Replacement last updated July 9 |
| |
| Permit Status - Interstate 90 |
Interstate 90 in both directions: from MN 74 to before Exit 257 single line traffic - alternating directions, major road construction, width limit in effect Width limit 12 ' 0 " — until August 31 Comment: Unbonded Concrete Overlay, Bridge & Culvert repair - I90 Eastbound from 2.2 miles East of Hwy 74 to 0.5 miles E of the W Jct Hwy 43 - May 3-13 East and westbound will have temporary and permanent lane closures - May 13 for duration, East and westbound will be one lane in each direction in the westbound lanes. last updated June 7 |
| |
| Permit Status - Interstate 90 |
Interstate 90 in both directions: from Exit 272 to Exit 275 roadway reduced to one lane, width limit in effect -- changing traffic patterns Width limit 14 ' 0 " — until November 1 Comment: Eastbound traffic shifted with head to head traffic on Westbound lanes last updated April 15 |
| |
| Permit Status - Interstate 94 |
Interstate 94 in both directions: from before North Dakota State Line to before US 75 bridge maintenance operations, width limit in effect, roadway reduced to one lane Width limit 12 ' 0 " — until August 15 Comment: On Interstate 94 eastbound and westbound from the Red River Bridge in Clay County to approximately 1/2 mile east will experience lane shifts across the bridges. Temporary lane restrictions will not be permitted between 6 a.m. and 8 a.m. and again during 4 p.m. and 6 p.m. during peak traffic flows. last updated July 12 |
| |
| Permit Status - Interstate 94 |
Interstate 94 in both directions: from US 71 to MN 238 road construction, single line traffic - alternating directions, work in the median, width limit in effect Width limit 14 ' 0 " daily — until tomorrow at about 10:30 AM CDT Comment: For more information:Click Here. Grading median inslopes and installing high tension median cable guardrail. Temporary lane restrictions and shoulder closures. last updated May 12 |
| |
| Permit Status - US 2 |
US 2: from Polk County Road 9 to Polk County Road 46 roadway reduced to two lanes, width limit in effect, long term road construction, emergency maintenance -- a mandatory speed limit is in force Width limit 8 ' 6 " Comment: Eastbound traffic will crossover to westbound lane, creating a two-way two-lane highway for 6,520 feet. This will remain in effect until further notice. US 2 is being reconstructed due to a landslide in 2008. last updated June 15 |
| |
| Permit Status - US 10 |
US 10: from US 75 to Clay County Road 82 work on underground services, roadway reduced to one lane, width limit in effect Width limit 11 ' 0 " — until Monday, at about 5:00 PM CDT Comment: Directional boring across Highway 10 underground cables placement. Cut street to expose existing utilities. last updated yesterday at 9:16 AM CDT |
| |
| Permit Status - US 10 |
US 10 in both directions: from Morrison County Road 13 to Morrison County Road 76 bridge construction, width limit in effect, delays, slow traffic, roadway reduced to two lanes, delays -- consider using an alternate route Comment: Consider using an alternate route during this weekTraffic is restricted to a single lane is each direction with Flaggers. WB entrance ramp from Morrison CR 76 to WB Hwy 10 is closed. EB exit ramp to Morrison CR 76 is also closed. 12 ft. width restrictions in both directions. Wide loads may check Hwy 27 E or W or Hwy 115 N. at Camp Ripley or Hwy 371 N. to Hwy 210 E or W. DELAYS on Friday July 30, of 15 min each as new beams are being placed. last updated yesterday at 11:05 AM CDT |
| |
| Permit Status - US 52 |
US 52 in both directions: from I-90 to US 63 roadway reduced to one lane, bridge maintenance operations, width limit in effect, length limit in effect Width limit 9 ' 0 ", Vehicle length limit 75.0 ft — until October 15 Comment: SP 5507-58 TH52 from 0.26 miles east of TH63 to 0.52 miles east of CSAH 1 Bridge rehabilitation on four bridges over CSAH 1 and Willow Creek last updated July 6 |
| |
| Permit Status - US 53 |
US 53: from US 71 to Canadian Border traffic restrictions in force — until September 7 Comment: At the International Falls /Canadian Border crossing, OS/OW loads will not be allowed to move on weekends from noon on Fridays to noon on Mondays. Restrictions apply from Memoral Day weekend to Labor Day weekend. last updated June 8 |
| |
| Permit Status - US 61 |
US 61 in both directions: from Winona County Road 15 to before Winona County Road 32 roadway reduced to one lane, road maintenance operations, width limit in effect Width limit 12 ' 0 " — until October 1 Comment: Bituminous Mill and Overlay, Pipe and Culvert Repairs - Intermittent lane closures and flaggers last updated July 27 |
| |
| Permit Status - US 61 |
US 61: between MN 74 and Wabasha County Road 84 gross weight limit in effect No vehicles over 80000 lbs Comment: This restriction will remain in effect until further notice. last updated April 16 |
| |
| Permit Status - US 71 |
US 71 in both directions: from Cottonwood County Road 25 to before MN 60 road closed, bridge construction, width limit in effect -- detour in operation, follow the signs Width limit 12 ' 0 " — until October 15 Comment: Bridge Replacement Windom TH 71 South: Outhbound detour from TH 71 onto Cottonwood County 17, south to Jackson County 30, east to rejoin TH 71. last updated July 28 |
| |
| Permit Status - US 71 |
US 71: from after Hubbard County Road 44 to MN 197, US 2 bridge construction, traffic restrictions in force because the route is temporarily closed to trucks with permits -- detour in operation, look out for flaggers, a mandatory speed limit is in force Width limit 11 ' 0 ", No vehicles over 80000 lbs — until June 15, 2011 Comment: On Hwy 197 in Bemidji to 1.7 miles south - Lane width restrictions, intermittent flag person, minor traffic delays. Detour on Hwy 71 starts July 6 through late August 2010. Detour: Hubbard Co.Rd. 9 north to Hubbard Co. Rd. 98 , then east to Beltrami Co. Rd. 2 to Hwy 71. SB traffic will use the same detour in reverse.DETOUR is posted for 9 Ton. Hwy 71 project home page last updated July 6 |
| |
| Permit Status - US 75 |
US 75: from after Norman County Road 51 to before Norman County Road 48 road closed, bridge construction, gross weight limit in effect -- detour in operation, follow the detour signs — until September 30 Comment: This project is one half mile south of Shelly on US 75. Legal weight on detour route. Detour as follows: Northbound 75 traffic at the Jct. of US 75 and Hwy 200 will go east for 14 miles on Hwy 200 to the jct. of Hwy 9, then north on Hwy 9 for 16 miles to the jct. of Polk county 1, go west for 13 miles on county 1 to the jct. of US 75. Southbound traffic will do the reverse. last updated June 24 |
| |
| Permit Status - US 169 |
US 169: from Aitkin County Road 37 to MN 210 road construction, width limit in effect -- detour in operation, pilot car in operation, look out for flaggers — until August 6 Comment: TH 169 from.23 miles N of Garrison to TH 210 in Aitkin and TH 210 from 1000' W of 8th Ave. to Aitkin Co Rd 12, Approx 1 mile E of Jct. TH 169 and TH 210 in Aitkin. Intersection of TH 210 and Aitkin Co 12 will remain Open. Bituminous mill & overlay, turn lane construction, culvet repair & replacement. DETOUR Scheduled for 8/2/10 - 8/5/10. Aitkin Co . Rd 76 from South Jct to N Jct. of TH 169. Widith Limit of 12'. Restriction Dates: Th 169 7/12/10 - 9/30/10 Length of Project 17.6 miles, TH 210: 7/26/1- - 8/6/10 Length of Project 1.7 miles last updated July 21 |
| |
| Permit Status - US 169 |
US 169: from US 2 to Itasca County Road 10 road construction, width limit in effect, single line traffic - alternating directions Width limit 12 ' 0 " — until August 31 Comment: Traffic signal work at 13th Avenue NE in Grand Rapids. Drainage work near RR bridge east of the Prairie River. Curb and gutter work just north of Pokegama Lake. last updated July 21 |
| |
| Permit Status - US 169 |
US 169: from Itasca County Road 10 to Itasca County Road 80 road closed, road construction, width limit in effect -- detour in operation Width limit 12 ' 0 " — until August 9 Comment: TH 169 from Taconite to Calumet will be closed starting July 20th. Traffic will be detoured to CSAH 10 south to CSAH 70 east to CSAH 12 north for a total of 7-8 miles. last updated July 20 |
| |
| Permit Status - US 169 |
US 169: from MN 65 to MN 65 road construction, width limit in effect, paving operations -- look out for flaggers, observe signs Width limit 12 ' 0 " — until October 30 Comment: On TH 169 between Pengilly and Keewatin, milling and culvert replacement on the four lane section. Daytime lane closures with flaggers. last updated July 21 |
| |
| Permits Closed - Interstate 35 |
Interstate 35 in both directions: from after Exit 32 Steele County Road 4 to Exit 41 Bridge Street roadway reduced to one lane, single line traffic - alternating directions, major road construction, closed for vehicles with permits -- consider using an alternate route — until September 14 Comment: Northbound and southbound traffic will be head-to-head on southbound lanes. Expect major delays during peak weekend travel times, including Friday and Sunday evenings. During backups use both lanes, take turns at merge. last updated July 27 |
| |
| Permits Closed - Interstate 35 |
Interstate 35: from Exit 246 Midway Road to Exit 252 Central Avenue closed for vehicles with permits -- detour in operation — until October 30 Comment: All trucks will be prohibited in Duluth between Boundary Avenue and Central Avenue. Trucks must follow posted detour route: I-35 to Duluth via County Road 13 , Hwy 194, to Hwy 53. For more information visit website www.state.mn.us/duluthmegaproject. last updated July 27 |
| |
| Permits Closed - US 14 |
US 14: at I-35 exit ramp closed, entrance ramp closed, closed for vehicles with permits because of construction work -- detour in operation — until November 5 Comment: Detour Rotes: Westbound Hwy 14 to Southbound I-35 ramp traffic will be detoured South on County 45 and West on Hwy 30 Northbound I-35 to Eastbound Hwy 14 traffic will be detoured east on Hwy 30 and North on County 45 last updated April 26 |